News

Contractual penalty of 84% of the salary, measured up to 10%

User Rating: 5 / 5

Star ActiveStar ActiveStar ActiveStar ActiveStar Active
 

Contractual penalty of 84% of the salary, measured up to 10%


Today, the Wrocław’s court has recognized our view in its entirety and by its judgment lowered the contractual penalty imposed by the Ordering Party (contract concluded under a public procurement procedure) for delays in the realisation of the contract for the completion of design and execution documentation of the building.
During the trial we were able to prove the absence of damage on the part of the Ordering Party, the absence of fault of our client and the relationship between the actions and omissions of the Ordering Party and the resulting delay.
Our work has been appreciated by the jury itself, planting the costs of legal representation in the amount of double rate.